Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 60.50% | 0.97% | 25.689% |
Major Bridge Works & ROB/ RUB | 15.63% | 0.23% | 10.683% |
Structures (elevated sections, reinforced earth) | 2.84% | 0.00% | 1.359% |
Electrical and Public Health Utilities | 0.56% | 0.00% | 0.380% |
Other Works | 20.46% | 0.35% | 1.573% |
Total | 100% | 1.547% | 39.68% |